Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : RAILWAY ELECTRIFICATION.
Project Name : SITARAMPUR-MUGHALSARAI RE.

Reported Date : 18-JUL-06

Monthly Report : 4 / 2002

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
240.40405.14

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
354.3800354.38

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/19980/00/0

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
05-OCT-990Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Others4/20020/0PendingNormal
Fund constraints4/20020/0PendingNormal
Delay in supply of indigenous equipments4/20020/0PendingNormal
Delay in Civil Works4/20020/0PendingNormal