Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : CENTRAL RAILWAYS.
Project Name : AMRAVATI-NARKHER NL(CR).

Reported Date : 13-AUG-19

Monthly Report : 6 / 2019

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
663.010858.96

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
719.661.125.55726.33

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/199912/20196/2019

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
.90

Ministry Review Date

LatestLastPhysical Progress (%)Status
95Completed

Monthly Status

Background Information

Line completed and commissioned in July 2012. Electrification has been commissioned.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Fund constraints3/20010/0PendingNormal
Forest Land12/20020/0PendingNormal
Award of contract3/20010/0PendingNormal
Others12/20020/0PendingNormal
Others12/20020/0PendingNormal