Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : RAILWAY ELECTRIFICATION.
Project Name : AMBALA-MORADABAD(RE).

Reported Date : 02-JUN-11

Monthly Report : 3 / 2011

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
152.21265283

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
267.394.930272.32

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/19980/00/0

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Fund constraints3/20010/0PendingNormal
Others3/20010/0PendingNormal