Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTHERN RAILWAY.
Project Name : UDHAMPUR-SRINAGAR-BARAMULLA (NL),NR.

Reported Date : 15-MAY-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
3701237012.2643780

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
42312.0216.81042328.83

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
8/202412/202412/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
30002939.33

Ministry Review Date

LatestLastPhysical Progress (%)Status
19-NOV-2422-DEC-04100Completed

Monthly Status

Background Information

Banihal-Sangaldan section (48 km) was dedicated to the nation by Honble PM on 20-02-24. Works on remaining Katra-Sangaldan section (63 km) are in an advanced stage of completion. This section includes 14 main tunnels and 5 escape tunnels wherein mining of both main and escape tunnels has been completed. Now, 639m of lining in MT is balance out of a total scope of 43.33 km, in challenging geology of Tunnel T-33 and T-42. More than 61 km of track linking has been completed out of the total scope of 67 km. Only 1 bridge remains out of the total 33 bridges. Total 4 stations are in between Katra- Sangaldan section. All stations completed.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Fund constraints3/20010/0PendingNormal
Forest Land4/20050/0PendingNormal
Forest Land4/20050/0PendingNormal
Others3/20010/0PendingNormal