Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTHERN RAILWAY.
Project Name : UDHAMPUR-SRINAGAR-BARAMULLA (NL),NR.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   1651.2

Time Overrun (Months)-    265

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
250037012.2643780

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
389313266.72114.342312.02

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
11/200212/202412/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
30002939.33

Ministry Review Date

LatestLastPhysical Progress (%)Status
19-NOV-2422-DEC-04100Ongoing

Monthly Status

Background Information

Out of 272Km, 209Km has already been commissioned. CRS inspection of Reasi-Sangaldan Section (46Km) was carried out from 26th to 28th June 2024 including Successful speed trail and CRS Authorization also obtained. Now 63 Km of section (katra to Sangaldan) is ready for dedicationBanihal-Sangaldan section (48 km) was dedicated to the nation by Honble PM on 20-02-24. Works on remaining Katra-Sangaldan section (63 km) are in an advanced stage of completion. This section includes 14 main tunnels and 5 escape tunnels wherein mining of both main and escape tunnels has been completed. Now, 639m of lining in MT is balance out of a total scope of 43.33 km, in challenging geology of Tunnel T-33 and T-42. More than 61 km of track linking has been completed out of the total scope of 67 km. Only 1 bridge remains out of the total 33 bridges. Total 4 stations are in between Katra- Sangaldan section. All stations completed.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Fund constraints3/20014/2002OverNormalResolved
Forest Land4/20055/2020OverNormalResolved
Forest Land4/20055/2020OverNormalResolved
Others3/20014/2002OverNormalResolved

Ongoing Milestone

Completed Milestone