Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTHERN RAILWAY.
Project Name : UDHAMPUR-SRINAGAR-BARAMULLA (NL),NR.

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   1546.36

Time Overrun (Months)-    261

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
250037012.2641159

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
34259.734335.2733638931

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
11/20028/20248/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
53104671.54

Ministry Review Date

LatestLastPhysical Progress (%)Status
23-MAR-2422-DEC-0498.5Ongoing

Monthly Status

Background Information

Banihal-Sangaldan section (48 km) was dedicated to the nation by Honble PM on 20-02-24. Works on remaining Katra-Sangaldan section (63 km) are in an advanced stage of completion. This section includes 14 main tunnels and 5 escape tunnels wherein mining of both main and escape tunnels has been completed. Now, 639m of lining in MT is balance out of a total scope of 43.33 km, in challenging geology of Tunnel T-33 and T-42. More than 61 km of track linking has been completed out of the total scope of 67 km. Only 1 bridge remains out of the total 33 bridges. Total 4 stations are in between Katra- Sangaldan section. All stations completed.Main Tunnel scope for Katra-Banihal section is 97,419m, mining of 24 m completed this month with cumulative progress of 97,305 m. Lining of 359 m completed this month with cumulative progress of 95,824 m. Escape Tunnel scope for Katra-Banihal section is 66,400m, mining 40 m completed this month with entire ET mining completed. Lining 895 m completed this month with cumulative progress of 59,954 m. Entire section including yards is on Ballast less Track (BLT). 7.7 km completed in this month with cumulative progress of 80.1 km out of 118 km. Total 7 stations are in between Katra- Banihal section. All stations nearly completed except Sawalkote station (90% work completed).

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Fund constraints3/20014/2002OverNormalResolved
Forest Land4/20055/2020OverNormalResolved
Forest Land4/20055/2020OverNormalResolved
Others3/20014/2002OverNormalResolved

Ongoing Milestone

Completed Milestone