Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : METROPOLITAN RAPID TRANSPORT PROJECTS.
Project Name : THANE-TURBHE-NERUL-VASHI(MTP).

Reported Date : 22-SEP-09

Monthly Report : 6 / 2009

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
403.390403.92

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
394.682.473.45400.6

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20000/06/2009

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Fund constraints3/20010/0PendingNormal
Forest Land3/20010/0PendingNormal
Delay in Civil Works9/20050/0PendingNormal