Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : CENTRAL RAILWAYS.
Project Name : MIRAJ-LATUR ROAD(GC),CR.

Reported Date : 28-APR-11

Monthly Report : 2 / 2011

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
225360.63816.4

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
775.1255.414.74845.26

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20013/20102/2011

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
700

Ministry Review Date

LatestLastPhysical Progress (%)Status
99Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Fund constraints3/20010/0PendingNormal
Forest Land12/20020/0PendingNormal