Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : METROPOLITAN RAPID TRANSPORT PROJECTS.
Project Name : BELAPUR-SEAWOOD-URAN ELECTRIFIED DOUBLE LINE(MTP).

Reported Date : 05-JUL-23

Monthly Report : 6 / 2023

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
495.4402980.41

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1920.57001920.57

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20040/03/2023

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1500

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Fund constraints3/20010/0PendingNormal
Award of contract10/20050/0PendingNormal
Award of contract10/20050/0PendingNormal
Others3/20010/0PendingNormal