Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EASTERN RAILWAYS.
Project Name : MANDARHILL-DUMKA-RAMPURHAT (NL),ER.

Reported Date : 13-AUG-19

Monthly Report : 6 / 2019

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1125.8901207.9

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1160.9614.025.11180.08

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20160/06/2019

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
275.120

Ministry Review Date

LatestLastPhysical Progress (%)Status
80Completed

Monthly Status

Background Information

Rampurhat – Mandarhill viaDumka (130 km) has been completed & commissioned on 28.09.2016 Subsequently the material modification works were sanctioned :- Rampurhat – Murarai (29.48 km) 3rd line Work was sanctioned in 2011-12 and cost of the project is Rs 224.05 cr. work is in progress in the railway land. Competent Authority nominates by State Government. Land acquisition is awaited by State Government ( West Bangal). Work is in progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Forest Land0/00/0PendingNormal
Forest Land0/00/0PendingNormal
Others0/00/0PendingNormal