Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : CENTRAL RAILWAYS.
Project Name : AHMEDNAGAR-PARLI VAIJNATH(NL) CR.

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   111.54

Time Overrun (Months)-    57

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2271.504805.17

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
3411.88300.26-13.543698.6

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20210/012/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
400.950

Ministry Review Date

LatestLastPhysical Progress (%)Status
83Ongoing

Monthly Status

Background Information

Total length of project -261.25 Km. Length commissioned till Dec-23 99.92 km. Ahmednagar–Narayandoh 12.275km Section Commissioned on 29.03.17 and Narayandoh to Solapurwadi 23.265 km section commissioned on 25.02.2019.Solapurwadi- Ashti section 30.649 km inspection done on 29.12.2021 and commissioned on 31.12.2021. Ashti to amalner 32.841 km Commissioned on 05.01.2024. However land acquisition and local hindrances are affecting the progress of works. Overall progress of project is as 58 numbers Major bridges out of 64 has been completed and 6 major bridges is in progress 252 numbers of Minor bridges out of 301 has been completed and 6 minor bridges in progress 110 RUBs out of 130 has been completed and 11 is in progress 18 ROBs out of 65 has been completed and 15 ROBs is in progress 6.912 L Cum ballast out of 7.52 L cum has been supplied and remaining is in progress 137.557 km Track linking completed out of 285.89 km. 421.485 L cum Earthwork completed out of 430.433 L cum and 8.948 L cum balance. There is a hindrance in Earthwork progress due to land acquisition. In Ahmednagar Beed Parli section 15.2665 Ha private land is balance to acquire. 0.2 Ha Forest land Stage- I clearance obtained. 20 EHV power line crossings out of 27 have been modified and 7 EHV modification not required. 568 LTHT crossings out of 599 have been modified. Electronic Interlocking of Narayandoh station is in progress and 75percentage indoor and outdoor work completed.Ahmednagar?Narayandoh(12.275km) Section Commissioned on 29.03.17 & Narayandoh to Solapurwadi (23.265 km) section commissioned on 25.02.2019.Solapurwadi- Ashti section (30.649 km) inspection done on 29.12.2021 and commissioned on 31.12.2021. Total land required = 1814.5822Ha, Acquired = 1803.293Ha. Balance land = 11.2892 Ha. Land acquisition completed in Ahmednagar dist. including acquisition of additional land. Moreover, Land acquisition completed in Beed district except acquisition of additional. Overall progress of project is as: 409.245 lac m3 earthwork out of 419.913 has been completed, 44 numbers Major bridges out of 64 has been completed, 244 numbers of Minor bridges out of 302 has been completed, 13 nos ROB out of 65 has been completed, 106 nos RUB out of 130 has been completed, 5.736 lac m3 Ballast supply out of 7.52 has been completed & 90.26 Km Track linking out of 285.89 has been completed.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Forest Land10/20050/0PendingNormal
Forest Land10/20050/0PendingNormal
Others3/20010/0PendingNormal

Ongoing Milestone

Completed Milestone