Reported Date :
13-FEB-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2025
|
Cost Overrun (%)- 118.24
|
Time Overrun (Months)-
57
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
4021.41 | 630.45 | 95.02 | 4746.88 |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
| Total length of project -261.25 Km. Length commissioned till Dec-23 99.92 km. Ahmednagar–Narayandoh 12.275km Section Commissioned on 29.03.17 and Narayandoh to Solapurwadi 23.265 km section commissioned on 25.02.2019.Solapurwadi- Ashti section 30.649 km inspection done on 29.12.2021 and commissioned on 31.12.2021. Ashti to amalner 32.841 km Commissioned on 05.01.2024. However land acquisition and local hindrances are affecting the progress of works. Overall progress of project is as 58 numbers Major bridges out of 64 has been completed and 6 major bridges is in progress 252 numbers of Minor bridges out of 301 has been completed and 6 minor bridges in progress 110 RUBs out of 130 has been completed and 11 is in progress 18 ROBs out of 65 has been completed and 15 ROBs is in progress 6.912 L Cum ballast out of 7.52 L cum has been supplied and remaining is in progress 137.557 km Track linking completed out of 285.89 km. 421.485 L cum Earthwork completed out of 430.433 L cum and 8.948 L cum balance. There is a hindrance in Earthwork progress due to land acquisition. In Ahmednagar Beed Parli section 15.2665 Ha private land is balance to acquire. 0.2 Ha Forest land Stage- I clearance obtained. 20 EHV power line crossings out of 27 have been modified and 7 EHV modification not required. 568 LTHT crossings out of 599 have been modified. Electronic Interlocking of Narayandoh station is in progress and 75percentage indoor and outdoor work completed. |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
Forest Land | 10/2005 | 0/0 | Pending | Normal | |
Forest Land | 10/2005 | 0/0 | Pending | Normal | |
Others | 3/2001 | 0/0 | Pending | Normal | |
| Ongoing Milestone | | Completed Milestone | | |