Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTH EAST CENTRAL RAILWAY.
Project Name : GONDIA-JABALPUR(GC),(SECR).

Reported Date : 07-OCT-21

Monthly Report : 9 / 2021

  

   

Total/Pending/Completed Milestone - 1 / 1 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
511.8617562005.25

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1829.5618.8718.731867.16

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
4/20203/20213/2021

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
100100

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Project completed and commissioned on 21.3.21

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Fund constraints3/20010/0PendingNormal
Forest Land3/20010/0PendingNormal