Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : WESTERN RAILWAY.
Project Name : SURENDRANAGAR-BHAVNAGAR(GC),WR.

Reported Date : 29-SEP-11

Monthly Report : 7 / 2011

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
437.4589.86563.25

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
544.07.25.03544.35

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20043/20050/0

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
40

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Fund constraints3/20010/0PendingNormal
Others3/20010/0PendingNormal