Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTHERN RAILWAY.
Project Name : NANGALDAM-TALWARA(NL),NR.

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   348.44

Time Overrun (Months)-    148

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
45020182017.96

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
845.230337.571182.8

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
7/201211/202411/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
450468.62

Ministry Review Date

LatestLastPhysical Progress (%)Status
31-DEC-2367Ongoing

Monthly Status

Background Information

• Work sanctioned via item no 3 pink book 1982-83. • Jan 1991: 1st block section Nangal Dam – Una Himachal (16.450 km) was commissioned. • May 2005: 2nd block section Una Himachal – Churaru Takrala (16.3 km) was commissioned. • July 2011: 3rd block section Churaru Takrala – Amb Andaura (11.162 km) was commissioned. • Jan 2019: 4th block section Amb Andaura – Daulatpur Chowk (15.425 km) was commissioned. • Daulatpur Chowk – Kartoli Punjab (5th block section 10.735 km): L section approved. Detailed estimate of 4th and 5th block section was sanctioned on 03.12.2008. Revised estimate was sanctioned on 13.03.2018. Land acquisition is under progress. Forest clearance of 2.32 Ha obtained out of 2.88 Ha. • Kartoli Punjab – Talwara (6th block section 14.923 Km): L – Section approved on 29.05.2019. Detailed estimate of 6th block section was sanctioned on 03.04.2019. Land acquisition under progress. Forest clearance of 20.86 Ha to be obtained. Mukerian – Talwara (29.16 km): Contract awarded on 05.05.2021 and work in progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Fund constraints3/20010/0PendingNormal
Forest Land11/20050/0PendingNormal
Forest Land11/20050/0PendingNormal
Others3/20010/0PendingNormal

Ongoing Milestone

Completed Milestone

 &nb