Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTHERN RAILWAY.
Project Name : NANGALDAM-TALWARA(NL),NR.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
20186032017.96

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1579.0425.3925.311629.74

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20251/20276/2027

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
654.130

Ministry Review Date

LatestLastPhysical Progress (%)Status
31-DEC-2375Ongoing

Monthly Status

Background Information

Progress during June’25: 1. Earthwork: 15,350Cum 2. Blanketing: 550 cum 3. Minor Bridge completed: 1 No. 4. Major Bridges:1 Nos 5. Viaduct: A. Raft: 6 Nos. B. Shaft: 11 Nos. C. Pier Cap: 11 Nos. D. Girder Erection: 7 Span E. Bearing Fixing: 8 Span F. Deck Slab Casting: 5 Span 6. Ballast Supply: 500 Cum 7. Track work completed: 0.30 KM.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Fund constraints3/20010/0PendingNormal
Forest Land11/20050/0PendingNormal
Forest Land11/20050/0PendingNormal
Others3/20010/0PendingNormal