Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTHERN RAILWAY.
Project Name : NANGALDAM-TALWARA(NL),NR.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   348.44

Time Overrun (Months)-    179

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
45002017.96

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1182.8361.7134.531579.04

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
7/20121/20276/2027

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
654.13553.14

Ministry Review Date

LatestLastPhysical Progress (%)Status
31-DEC-2370Ongoing

Monthly Status

Background Information

Progress during March’25: Earthwork( 4250 Cum), Blanketing(900 cum), Minor Bridge ( 2 Nos.), Ballast Supply (1100 Cum), Viaduct( Raft 12 Nos., Pier Shaft 13 Nos., Pier Cap 10 Nos., Girder Erection 18 Spans, Deck Slab 24 Spans completed during Mar’25. Other activities of the project in progress at different locations.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Fund constraints3/20010/0PendingNormal
Forest Land11/20050/0PendingNormal
Forest Land11/20050/0PendingNormal
Others3/20010/0PendingNormal

Ongoing Milestone

Completed Milestone