Sector Name : RAILWAYS.
Agency Name : SOUTH WESTERN RAILWAY.
Project Name : KADUR-CHIKMAGALUR-SAKLESHPUR (NL),(SWR).

Reported Date : 17-JAN-14

Monthly Report : 11 / 2013

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
157262.82333.5

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
290.2732.297.82330.38

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20123/20123/2013

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
100

Ministry Review Date

LatestLastPhysical Progress (%)Status
05-OCT-99100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Fund constraints3/20010/0PendingNormal
Forest Land11/20050/0PendingNormal