Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTHERN RAILWAY.
Project Name : KARUR-SALEM(NL),SR.

Reported Date : 13-AUG-19

Monthly Report : 6 / 2019

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
155.550920

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
863.24.30863.54

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
0/00/06/2019

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
98Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Fund constraints3/20010/0PendingNormal
Forest Land3/20010/0PendingNormal
Award of contract7/20020/0PendingNormal
Others11/20050/0PendingNormal