Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTH CENTRAL RAILWAY.
Project Name : NANDYAL-YERRAGUNTLA(NL),SCR.

Reported Date : 07-OCT-21

Monthly Report : 9 / 2021

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
164.36966.431050

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1147.2201.451148.67

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/20090/03/2019

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
60

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Completed

Monthly Status

Background Information

Total Project Commissioned and dedicated to the nation by the Honble MR by flagging off the new train from Nandyal station to Kadapa station on 23.8.16. 2.1.1 Entire length completed and last phase commissioned in August 2016. CRS inspection completed on 28.02.19 and authorization received on 01.02.19. Nandyal Jn Cabin to Nandyal (2.324 Km) commissioned on 14.03.19 after NI.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Fund constraints3/20010/0PendingNormal
Forest Land10/20050/0PendingNormal