Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH EAST FRONTIER RAILWAY.
Project Name : BPUTRA BRIDGE AT BOGIBIL AND LINK LINES NEFR.

Reported Date : 07-FEB-19

Monthly Report : 12 / 2018

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
3230.0248575820

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
5022.67253.6121.815298.09

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
4/20080/06/2018

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
2150

Ministry Review Date

LatestLastPhysical Progress (%)Status
22-DEC-04100Completed

Monthly Status

Background Information

Land Acquisition (Hect.):(Scope=505.94/Physical progress=505.94)=100% Earth Work (Lakh Cum.):(Scope=288.52/Physical progress=288.52)=100% Formation (Km.):(Scope=70.6/Physical progress=70.6)=100% Major Bridge - Sub Strc. (Nos.):(Scope=17/Physical progress=17)=100% Major Bridge - Super Strc. (Nos.):(Scope=17/Physical progress=17)=100 % Minor Bridge (Nos.):(Scope=104/Physical progress=104)=100 % ROB (Nos.):(Scope=3/Physical progress=3)=100 % RUB (Nos.) :(Scope=7/Physical progress=7)=100 % Track Linking - Main Line (Km.):(Scope=92.65/Physical progress=92.65)=100 % Main Bridge-Sub. Strc. - Wells (Nos.):(Scope=42/Physical progress=42)=100 % Main Bridge-Sub.Strc.-Pier/Abutment(Nos.):(Scope=42/Physical progress=42)=100 % Main Bridge-Sup Strc. - Girder Fabrication (Nos. of Spans):(Scope=41/Physical progress=41)=100 % Main Bridge-Sup Strc. - Girder Assembly (Nos. of Spans) :(Scope=41/Physical progress=41)=100% Main Bridge-Sup. Strc. - Girder Launching (Nos. of Spans):(Scope=41/Physical progress=41)=100% Boulder (Lakh Cum.):(Scope=22.35/Physical progress=22.35)=100 % Main Bridge- Sup Strc. - Girder Lowering (Nos. of Spans):(Scope=41/Physical progress=41)=100% Main Bridge-Sup Strc.-Deck Concreting(Rm):(Scope=4940/Physical progress=4940)=100% Road Viaduct - South Bank - Pile Foundation (Group) (Nos.):(Scope=34/Physical progress=34)=100 % Road Viaduct - South Bank - Pier / Abutment (Nos.):(Scope=34/Physical progress=34)=100% Road Viaduct - South Bank - Sup Strc. Girder (Nos.of Spans):(Scope=34/Physical progress=34)=100 % Road Viaduct - South Bank- Sup Strc. (Deck Slab) (Nos. of Spans):(Scope=34/Physical progress=34)=100 % Road Viaduct - North Bank - Pile Foundation (Group) (Nos.):(Scope=34/Physical progress=34)=100 % Road Viaduct - North Bank - Pier / Abutment (Nos.):(Scope=34/Physical progress=34)=100% Road Viaduct - North Bank - Sup. Strc. Girder (Nos. of Spans):(Scope=34/Physical progress=34)=100% Road Viaduct - North Bank- Sup Strc. (Deck Slab) (Nos. of Spans):(Scope=34/Physical progress=34)=100% Overall Progress (Physical):100%

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Fund constraints12/20042/2018PendingNormal
Fund constraints12/20042/2018PendingNormal
Forest Land12/20042/2018PendingNormal
Forest Land12/20042/2018PendingNormal
Others3/20012/2018PendingNormal