Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTH CENTRAL RAILWAY.
Project Name : MUNEERABAD-MAHABOOBNAGAR(NL),SCR.

Reported Date : 25-APR-24

Monthly Report : 4 / 2024

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
172303381.68

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2238.110294.082532.19

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20002/20232/2023

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Entire section commissioning completed in Feb-2023.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Fund constraints3/20010/0PendingNormal
Forest Land10/20050/0PendingNormal
Forest Land10/20050/0PendingNormal