Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH EAST FRONTIER RAILWAY.
Project Name : NEW JALPAIGURI-NEW BONGAIGAON (GC),NEFR.

Reported Date : 25-NOV-10

Monthly Report : 9 / 2010

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
536.8501010

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
998.56.95.051005.5

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20030/09/2010

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
50

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Award of contract10/20020/0PendingNormal
Fund constraints10/20050/0PendingNormal
Fund constraints10/20050/0PendingNormal