Reported Date :
13-FEB-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2025
|
Cost Overrun (%)- 3230.57
|
Time Overrun (Months)-
202
|
Total/Pending/Completed Milestone -
9
/
8
/
1
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
| (A)Govindgarh - Baghwar - Rampur Naikin(22.35 Km): (i) Major bridges out of total 5 bridges, 01- fully completed, 02- substructure completed and superstructure is in progress and substructure work in progress in 2 bridges (ii) Minor bridges- 36/41 completed and work in progress on 5 bridges (iii) Formation - 11 km ready. Track linking is in progress. 9.5(prog.)/10.4 lac cum E/W done. 26000/80000 m3 blanketing done. 62000 cum ballast supplied. (B) Rampur Naiken – Churhat - Sidhi (46.75 Km) (i) Major bridges: -out of total 8 bridges, 01-fully completed, 02- substructure completed and 01- work in progress. (ii) Viaduct (5x76.2m + 1x76.2m)– 72/90 pile, 07/08 pile cap & 4/8 nos. Pier completed. Minor bridges- 47/96 completed. (v) Earthwork – 8.5/18.43 Lm3 done & Blanketing- 0.12/1.47 Lm3 done. 64000 cum ballast supplied. (C)Sidhi - Singrauli: (KM 88 to 166). Project |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
Forest Land | 9/2001 | 0/0 | Pending | Normal | |
| Ongoing Milestone | | Completed Milestone | | |