Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : WEST CENTRAL RAILWAY.
Project Name : LALITPUR-SATNA-REWA-SINGRULI NL, (NCR).

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   3230.57

Time Overrun (Months)-    202

Total/Pending/Completed Milestone - 9 / 8 / 1

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
247.6608248.5

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2427.3316.6756.342500.34

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
5/20080/03/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Ongoing

Monthly Status

Background Information

(A)Govindgarh - Baghwar - Rampur Naikin(22.35 Km): (i) Major bridges out of total 5 bridges, 01- fully completed, 02- substructure completed and superstructure is in progress and substructure work in progress in 2 bridges (ii) Minor bridges- 36/41 completed and work in progress on 5 bridges (iii) Formation - 11 km ready. Track linking is in progress. 9.5(prog.)/10.4 lac cum E/W done. 26000/80000 m3 blanketing done. 62000 cum ballast supplied. (B) Rampur Naiken – Churhat - Sidhi (46.75 Km) (i) Major bridges: -out of total 8 bridges, 01-fully completed, 02- substructure completed and 01- work in progress. (ii) Viaduct (5x76.2m + 1x76.2m)– 72/90 pile, 07/08 pile cap & 4/8 nos. Pier completed. Minor bridges- 47/96 completed. (v) Earthwork – 8.5/18.43 Lm3 done & Blanketing- 0.12/1.47 Lm3 done. 64000 cum ballast supplied. (C)Sidhi - Singrauli: (KM 88 to 166). Project It is an alternative route for mineral loading and connecting to tourist places in MP & UP, Development of tribal area.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Forest Land9/20010/0PendingNormal

Ongoing Milestone

Completed Milestone