(A)Govindgarh - Baghwar - Rampur Naikin(22.35 Km): (i) Major bridges out of total 5 bridges, 01- fully completed, 02- substructure completed and superstructure is in progress and substructure work in progress in 2 bridges (ii) Minor bridges- 36/41 completed and work in progress on 5 bridges (iii) Formation - 11 km ready. Track linking is in progress. 9.5(prog.)/10.4 lac cum E/W done. 26000/80000 m3 blanketing done. 62000 cum ballast supplied. (B) Rampur Naiken – Churhat - Sidhi (46.75 Km) (i) Major bridges: -out of total 8 bridges, 01-fully completed, 02- substructure completed and 01- work in progress. (ii) Viaduct (5x76.2m + 1x76.2m)– 72/90 pile, 07/08 pile cap & 4/8 nos. Pier completed. Minor bridges- 47/96 completed. (v) Earthwork – 8.5/18.43 Lm3 done & Blanketing- 0.12/1.47 Lm3 done. 64000 cum ballast supplied. (C)Sidhi - Singrauli: (KM 88 to 166). Project | It is an alternative route for mineral loading and connecting to tourist places in MP & UP, Development of tribal area. |