Entire Section Jaynagar - Narkatiaganj - Gaunaha ( 282 Km) commissioned .
a) Jaynagar – Darbhanga (68 Km):- Commissioned on 24.09.2007
b) Darbhanga – Sitamarhi (68 Km):- Commissioned on 27.09.2008
c) Sitamarhi – Baragania (28 Km):- Commissioned on 30.07.2010
d) Baragania- Chauradano (30 Km) :- Commissioned on 26.01.2013
e) Chauradano – Raxaul (24 Km):- Commissioned on 22.02.2014
f) Raxaul - Narkatiyaganj (42km) :- Commissioned on 12.08.2018.Section handed over to Open line on 18.01.19.
g) Narkatiyaganj – Amolwa (12 Km):- Commissioned on 20.01.23.
h) Amolwa – Gaunaha (10 km):- Commissioned on 29.12.23.
| a) Jaynagar – Darbhanga (68 Km): Commissioned on 24.09.2007
b) Darbhanga – Sitamarhi (68 Km): Commissioned on 27.09.2008
c) Sitamarhi – Baragania (28 Km): Commissioned on 30.07.2010
d) Baragania- Chauradano (30 Km) : Commissioned on 26.01.2013
e) Chauradano – Raxaul (24 Km): Commissioned on 22.02.2014
f) Raxaul-Narkatiyaganj (42km) : Commissioned on 12.08.2018.Section handed over to Open line on
18.01.19.
g) Narkatiyaganj – Amolwa (12 Km): Commissioned on 20.01.23.
h) Narkatiyaganj - Amolwa (12 km)-
Commissioned on 20.01.23
i)- Amolwa – Gaunaha (10 km)-
E/W - Completed & Blanketing - Work in progress , Minor Br - 06 no Br completed out of total 09 no Br. Track linking - Balance track linking is to be done on major br. Approaches, OHE work in progress. Target month of commissioning - Sep23
|