Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST CENTRAL RAILWAYS.
Project Name : JAYANAGAR-DARBHANGA-NARKATIA GANJ(GC),ECR.

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   284.94

Time Overrun (Months)-    141

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
324.73967.291250

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1155.440.9910.081206.47

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20120/012/2023

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
250

Ministry Review Date

LatestLastPhysical Progress (%)Status
99Ongoing

Monthly Status

Background Information

Entire Section Jaynagar - Narkatiaganj - Gaunaha ( 282 Km) commissioned . a) Jaynagar – Darbhanga (68 Km):- Commissioned on 24.09.2007 b) Darbhanga – Sitamarhi (68 Km):- Commissioned on 27.09.2008 c) Sitamarhi – Baragania (28 Km):- Commissioned on 30.07.2010 d) Baragania- Chauradano (30 Km) :- Commissioned on 26.01.2013 e) Chauradano – Raxaul (24 Km):- Commissioned on 22.02.2014 f) Raxaul - Narkatiyaganj (42km) :- Commissioned on 12.08.2018.Section handed over to Open line on 18.01.19. g) Narkatiyaganj – Amolwa (12 Km):- Commissioned on 20.01.23. h) Amolwa – Gaunaha (10 km):- Commissioned on 29.12.23. a) Jaynagar – Darbhanga (68 Km): Commissioned on 24.09.2007 b) Darbhanga – Sitamarhi (68 Km): Commissioned on 27.09.2008 c) Sitamarhi – Baragania (28 Km): Commissioned on 30.07.2010 d) Baragania- Chauradano (30 Km) : Commissioned on 26.01.2013 e) Chauradano – Raxaul (24 Km): Commissioned on 22.02.2014 f) Raxaul-Narkatiyaganj (42km) : Commissioned on 12.08.2018.Section handed over to Open line on 18.01.19. g) Narkatiyaganj – Amolwa (12 Km): Commissioned on 20.01.23. h) Narkatiyaganj - Amolwa (12 km)- Commissioned on 20.01.23 i)- Amolwa – Gaunaha (10 km)- E/W - Completed & Blanketing - Work in progress , Minor Br - 06 no Br completed out of total 09 no Br. Track linking - Balance track linking is to be done on major br. Approaches, OHE work in progress. Target month of commissioning - Sep23

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Fund constraints11/20010/0PendingNormal

Ongoing Milestone

Completed Milestone

   </