Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTHERN RAILWAY.
Project Name : CHANDIGARH-LUDHIANA(NEW BG LINE),NR.

Reported Date : 13-DEC-13

Monthly Report : 10 / 2013

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
248.44576.271115.21

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
945.924.452.56972.91

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20121/20134/2013

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
300

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Others3/20050/0PendingNormal