Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH EAST FRONTIER RAILWAY.
Project Name : KATIHAR - JOGBANI (GC)(NEFR).

Reported Date : 13-AUG-19

Monthly Report : 6 / 2019

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
792.4601320

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
944.78.020944.8

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20100/06/2019

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
17.39Completed

Monthly Status

Background Information

Land Acquisition (Hect.):(Scope=341.99/Physical progress=17.11)=5% Earth Work (Lakh Cum.):(Scope=39.97/Physical progress=6.35)=15.89% Formation (Km.):(Scope=43.43/Physical progress=5.06)=11.65% Major Bridge - Sub Strc. (Nos.):(Scope=13/Physical progress=5)=38.46% Major Bridge - Super Strc. (Nos.):(Scope=13/Physical progress=7)=53.85% Minor Bridge (Nos.):(Scope=95/Physical progress=3)=3.16% Track Linking - Main Line (Km.):(Scope=51.042/Physical progress=34.25)=67.1%

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Fund constraints10/20052/2018PendingNormal
Fund constraints10/20052/2018PendingNormal
Award of contract10/20022/2010PendingNormal