Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTHERN RAILWAY.
Project Name : KUTTIPURAM-CALICUT INCLD. SHORANUR-M-LORE (DL) (SR).

Reported Date : 02-JUN-11

Monthly Report : 3 / 2011

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
178.760219.94

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
190.4900190.49

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
0/00/00/0

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Award of contract3/20020/0PendingNormal
Delay in supply of indigenous equipments10/20020/0PendingNormal
Delay in Civil Works7/20020/0PendingNormal
Others8/20020/0PendingNormal
Forest Land11/20040/0PendingNormal
Forest Land11/20040/0PendingNormal