Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH EASTERN RAILWAY.
Project Name : GONDA-GORAKHPUR LOOP WITH ANAND NAGAR-NAUTANWA GC (NER).

Reported Date : 13-AUG-15

Monthly Report : 6 / 2015

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
863.2301072.51

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
780.91107.960888.87

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
0/00/05/2015

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
100129.97

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks