Sector Name : RAILWAYS.
Agency Name : EAST CENTRAL RAILWAYS.
Project Name : KHAGARIA-KUSHESHWAR ASTHAN (NL) (ECR).

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   277.26

Time Overrun (Months)-    24324

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
162.87614.45614.45

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
389.9736.190426.16

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
0/00/012/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
650

Ministry Review Date

LatestLastPhysical Progress (%)Status
50Ongoing

Monthly Status

Background Information

a) Khagaria - Kamathan - Alauli (19 km):- section opened for Goods traffic on 04.05.2022. b) Alauli - Kusheswarsthan(23.1km) - Hydrological study has been completed and report has been submitted by RITES Ltd in Jan,22. Additional provisions like 02 Nos. of important bridges ( 8x61.0m OWG & 11X61.0m OWG), 04 Nos. of major bridges & 16 Nos. of minor bridges etc. have been recommended in the above report. Accordingly, estimate has been revised for total cost of Rs. 1511.08 Cr. and sent to Railway Board on 19.05.2023. Location of Kusheshwar Asthan Yard under revision due to change in Alignment. Target month of commissioning - Dec’26 "a) Khagaria - Kamathan - Alauli (19 km):- section opened for Goods traffic on 04.05.2022. b) Alauli - Kusheswarsthan(23.1km) - Hydrological study has been completed and report has been submitted by RITES Ltd in Jan,22. Additional provisions like 02 Nos. of important bridges ( 8x61.0m OWG & 11X61.0m OWG), 04 Nos. of major bridges & 16 Nos. of minor bridges etc. have been recommended in the above report. Accordingly, estimate is being revised for total cost of Rs. 1511.08 Cr. and sent to Railway Board on 19.05.2023. Target month of commissioning - Mar¿25"

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Forest Land4/20050/0PendingNormal