Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : RAILWAY ELECTRIFICATION.
Project Name : ELECTRIFICATION OF ERNAKULAM-TRIVANDRUM (RE).

Reported Date : 26-SEP-07

Monthly Report : 5 / 2007

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
162.030196.15

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
0161.60161.6

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
8/20030/00/0

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks