Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTHERN RAILWAY.
Project Name : TIRUCHIRAPPALI-NAGORE-KARAIKKAL(SR)(GC).

Reported Date : 14-JUL-22

Monthly Report : 6 / 2022

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
303.9801549.09

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
723.961.352.31727.62

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20200/03/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
121.80

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Completed

Monthly Status

Background Information

All sections commissioned except NGT-Thirukuvalai-TTP NL (38 Km) and PEM-KIK New Line (23 km). Regarding Peralam-Karaikal, EW & bridge works are in progress. Total extent of 4.42 Ha of land is required for this New Line TDC: December 2023. The revised estimate including Northern connectivity for KIKP submitted to Board with GM approval on 13.12.2021.Board has returned the RE with observations. Being attended. The KIK-PEM NL project is included in Vision 2024. Reg. TTP-NGT NL, works are in progress and the TDC is 31.03.25.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Others10/20050/0PendingNormal