Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTHERN RAILWAY.
Project Name : QUILON-TIRUNELVELI-TENKASI-VIRUDHUNAGAR(SR)(GC).

Reported Date : 13-AUG-19

Monthly Report : 6 / 2019

  

   

Total/Pending/Completed Milestone - 6 / 6 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
28001220

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
938.631.272.38942.28

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
0/00/06/2019

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
50

Ministry Review Date

LatestLastPhysical Progress (%)Status
99Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Forest Land11/20050/0PendingNormal