Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH EAST FRONTIER RAILWAY.
Project Name : NEW MAYNAGURI TO JOGIGHOPA VIA CHANGRABANDHA (NL),NEFR.

Reported Date : 08-MAR-22

Monthly Report : 2 / 2022

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1180.1904541.38

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
3804.54146.1432.643983.32

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20080/012/2021

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
99.85Completed

Monthly Status

Background Information

Land Acquisition (Hect.):(Scope=1064.707/Physical progress=1064.707)=100% Earth Work (Lakh Cum.):(Scope=213.42/Physical progress=213.42)=100% Formation (Km.):(Scope=288.885/Physical progress=288.885)=100% Major Bridge - Sub Strc. (Nos.) :(Scope=68/Physical progress=68)=100% Major Bridge - Super Strc. (Nos.) :(Scope=68/Physical progress=68)=100% Minor Bridge (Nos.):(Scope=376/Physical progress=376)=100% ROB (Nos.):(Scope=11/Physical progress=11)=100% RUB (Nos.):(Scope=24/Physical progress=24)=100% LHS (Nos.):(Scope=224/Physical progress=224)=100% L-Xing (Nos.):(Scope=82/Physical progress=82)=100% Tunnels(Rm):(Scope=1056.74/Physical Progress=1056.74)=100% Track Linking - Main Line (Km.):(Scope=288.883/Physical progress=288.883)=100% Station Building (Nos.):(Scope=21/Physical progress=21)=100%

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Fund constraints11/20050/0PendingNormal
Forest Land10/20050/0PendingNormal