Reported Date :
12-FEB-24
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2024
|
Cost Overrun (%)- 36.22
|
Time Overrun (Months)-
72
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
The main work Tarakeshwar – Bishnupur (82.47 Km) – New line - Work was sanctioned in 2000-01 and cost of the project is Rs 479.20 Cr.
Tarkeshwar –Goghat (32.85 Km) New line – Commissioned on 06.03.2016.
Maynapur – Bishnupur (22.68 Km) New line – Commissioned on 16.09.2012.
Goghat – Kamarpukur (5.50 Km) was completed during 2018-19 except 950m stretch where the work is stopped by local villagers at Bhabadighi pond since March’2017. The matter is being pursued with State Govt.
Balance section:
(a) Kamarpukur – Jayrambati (5.19 KM) part of Tarakeshwar – Bishnupur (82.47 Km) project falling in Hoogly District: Target: Mar’2025. Physical Progress- 32%. Work in progress.
(b) Jayrambati – Maynapur (14.62 Km) part of Tarakeshwar – Bishnupur (82.46 Km) project falling in Bankura District:- Target – Dec’2024. Physical Progress- 66%. Work in progress.
CRITICAL ISSUE:
i. Local public frequently stops work (Land issues demand of additional RUBV/Bridge)
ii. Removal of Electrical infringement: 39 infringements removed out of 40. Work for balance 01
Infringement removal in progress (TDC-10.04.2024).
iii. Elec (TRD) tender finalized & LOA issued on 07.07.2023 & drawing under preparation and
Elec (G) tender opened on 15.06.23. LOA issued on 14.08.2023. TRD foundation started from
Maynapur side. 37 nos OHE mast foundation casted till date as per available bed.
iv. Tender for S&T work opened on 07.08.2023 & under finalisation.
| Balance section (a) Kamarpukur – Jairambati (5.19 KM) part of Tarakeshwar – Bishnupur (82.47 Km) project falling in Hoogly District: Targeted in 2023-24. Work in progress.
CRITICAL ISSUE:
1. Land acquisition for 12.10 Ha of land for 2.545 km stretch.
2. Removal of 16/20 WBSEDCL infringement.
(b) Jairambati – Mayonapur (14.62 Km) part of Tarakeshwar – Bishnupur (82.47 Km) project falling in Bankura District:- Targeted in 2023-24. Work in progress.
CRITICAL ISSUE:
1. Local disturbance frequently stops work (Land issues)
2. Removal of Electrical infringement 20/38 remaining.
3. Tenders for TRD & Genl opened on 19.06.23 & under finalization.
4. Tender for S&T yet to be invited.
|
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
Forest Land | 10/2005 | 0/0 | Pending | Normal | |
| Ongoing Milestone | | Completed Milestone | | & |