Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EASTERN RAILWAYS.
Project Name : TARAKESWAR - BISHNUPUR NEW BG LINE (NL), ER.

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   36.22

Time Overrun (Months)-    72

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1188.9101619.51

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
995.7313.1417.681026.55

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20193/20253/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
177.20

Ministry Review Date

LatestLastPhysical Progress (%)Status
75Ongoing

Monthly Status

Background Information

The main work Tarakeshwar – Bishnupur (82.47 Km) – New line - Work was sanctioned in 2000-01 and cost of the project is Rs 479.20 Cr. Tarkeshwar –Goghat (32.85 Km) New line – Commissioned on 06.03.2016. Maynapur – Bishnupur (22.68 Km) New line – Commissioned on 16.09.2012. Goghat – Kamarpukur (5.50 Km) was completed during 2018-19 except 950m stretch where the work is stopped by local villagers at Bhabadighi pond since March’2017. The matter is being pursued with State Govt. Balance section: (a) Kamarpukur – Jayrambati (5.19 KM) part of Tarakeshwar – Bishnupur (82.47 Km) project falling in Hoogly District: Target: Mar’2025. Physical Progress- 32%. Work in progress. (b) Jayrambati – Maynapur (14.62 Km) part of Tarakeshwar – Bishnupur (82.46 Km) project falling in Bankura District:- Target – Dec’2024. Physical Progress- 66%. Work in progress. CRITICAL ISSUE: i. Local public frequently stops work (Land issues demand of additional RUBV/Bridge) ii. Removal of Electrical infringement: 39 infringements removed out of 40. Work for balance 01 Infringement removal in progress (TDC-10.04.2024). iii. Elec (TRD) tender finalized & LOA issued on 07.07.2023 & drawing under preparation and Elec (G) tender opened on 15.06.23. LOA issued on 14.08.2023. TRD foundation started from Maynapur side. 37 nos OHE mast foundation casted till date as per available bed. iv. Tender for S&T work opened on 07.08.2023 & under finalisation. Balance section (a) Kamarpukur – Jairambati (5.19 KM) part of Tarakeshwar – Bishnupur (82.47 Km) project falling in Hoogly District: Targeted in 2023-24. Work in progress. CRITICAL ISSUE: 1. Land acquisition for 12.10 Ha of land for 2.545 km stretch. 2. Removal of 16/20 WBSEDCL infringement. (b) Jairambati – Mayonapur (14.62 Km) part of Tarakeshwar – Bishnupur (82.47 Km) project falling in Bankura District:- Targeted in 2023-24. Work in progress. CRITICAL ISSUE: 1. Local disturbance frequently stops work (Land issues) 2. Removal of Electrical infringement 20/38 remaining. 3. Tenders for TRD & Genl opened on 19.06.23 & under finalization. 4. Tender for S&T yet to be invited.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Forest Land10/20050/0PendingNormal

Ongoing Milestone

Completed Milestone

&