Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTHERN RAILWAY.
Project Name : JIND-SONEPAT (NL),NR.

Reported Date : 13-AUG-19

Monthly Report : 6 / 2019

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
238.560790

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
785.36.390785.75

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20120/06/2019

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
110

Ministry Review Date

LatestLastPhysical Progress (%)Status
18-JUL-1999Completed

Monthly Status

Background Information

CRS inspection done on 20.01.2016 and 21.01.2016 and section opened for traffic. Passenger service also started from 26.06.16. Section handed over to open line.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks