Reported Date :
13-FEB-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2025
|
Cost Overrun (%)- 74.11
|
Time Overrun (Months)-
213
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
3496.72 | 988.96 | 141.84 | 4627.52 |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
Daspalla-Buguda (15.175 Km): 145800 cum earthwork along with 153m tunnel excavation and 18m lining completed in Mar-25.
Buguda-Baniguchha (18.48 Km): 280800 cum earthwork & 2 minor bridges along with 165m tunnel excavation and 132m lining completed in Mar-25.
Baniguchha-Purunakatak (41.435 Km): 268650 cum earthwork & 2 minor bridges along with 122m tunnel excavation and 343.5m lining and 22m ballastless track laying completed in Mar-25.
Boudh-Purunakatak (26.888 Km): CRS inspection completed & authorisation received for Boudh-Champapur-Purunakatak (26.888 Km) section on 26.03.2025. | Daspalla-Buguda(22km): 140000 cum earthwork completed in Mar-24.
Buguda-Baniguchha(18Km): 295000 cum earthwork alongwith 3 minor bridges completed in Mar-24.
Baniguchha-Purunakatak(41Km): 73800cum of earthwork alongwith 2 minor bridge and 507.40m tunnel excavation in Mar-24.
Purunakatak-Boudh(22km): 21400cum of earthwork alongwith 1 major bridge completed in Mar-24.
Boudh-Sonepur(43km): Engine rolling successfully completed between Sonepur-Purunapani-Jharmunda (29.75 Km) in Mar-24. |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |