Daspalla-Buguda (15.175 Km): 98000 cum earthwork and 7500 cum blanketing along with 197.8m tunnel excavation and 28.6m lining completed in May-25. Breakthrough in tunnel T2 (2620m) achieved on 28.05.25.
Buguda-Baniguchha (18.48 Km): 160000 cum earthwork and 1 minor bridge along with 259.5m tunnel lining completed in Apr-25. Viaduct 338A (11x24.4m CG) work completed. Launching of two spans (24.4m CG) girder in Br.302 alongwith three spans (24.4m CG) deck slab casting completed in May-25.
Baniguchha-Purunakatak (41.435 Km): 247970 cum earthwork & 2 minor bridges along with 84.5m tunnel excavation and 435.1m lining completed in May-25. Launching of seven spans (24.4m CG) girder in Br.435A completed. | Daspalla-Buguda(22km): 140000 cum earthwork completed in Mar-24.
Buguda-Baniguchha(18Km): 295000 cum earthwork alongwith 3 minor bridges completed in Mar-24.
Baniguchha-Purunakatak(41Km): 73800cum of earthwork alongwith 2 minor bridge and 507.40m tunnel excavation in Mar-24.
Purunakatak-Boudh(22km): 21400cum of earthwork alongwith 1 major bridge completed in Mar-24.
Boudh-Sonepur(43km): Engine rolling successfully completed between Sonepur-Purunapani-Jharmunda (29.75 Km) in Mar-24. |