Daspalla-Buguda (15.175 Km): 76000 cum earthwork and 9800 cum blanketing along with 33.3m tunnel lining completed in Jun-25.
Buguda-Baniguchha (18.48 Km): 110000 cum earthwork and 2 minor bridges along with 251.2m tunnel lining completed in Jun-25. Launching of 11 spans (24.4m CG) girder in Br.302 alongwith 5 spans (24.4m CG) deck slab casting completed in Jun-25.
Baniguchha-Purunakatak (41.435 Km): 74166 cum earthwork & 3 minor bridges along with 85m tunnel excavation and 247.4m lining completed in Jun-25. Launching of 6 spans (24.4m CG) girder in Br.435A completed.
Sonepur-Purunakatak (73 Km): Hon’ble Prime Minister of India on 20.06.2025 has inaugurated the newly constructed single line of 73 Km between Sonepur-Boudh-Purunakatak of Khurda Bolangir project and also flagged off the train service between Bolangir-Sonepur-Boudh-Purunakatak. | Daspalla-Buguda(22km): 140000 cum earthwork completed in Mar-24.
Buguda-Baniguchha(18Km): 295000 cum earthwork alongwith 3 minor bridges completed in Mar-24.
Baniguchha-Purunakatak(41Km): 73800cum of earthwork alongwith 2 minor bridge and 507.40m tunnel excavation in Mar-24.
Purunakatak-Boudh(22km): 21400cum of earthwork alongwith 1 major bridge completed in Mar-24.
Boudh-Sonepur(43km): Engine rolling successfully completed between Sonepur-Purunapani-Jharmunda (29.75 Km) in Mar-24. |