Reported Date :
12-FEB-24
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2024
|
Cost Overrun (%)- 29.71
|
Time Overrun (Months)-
213
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
2571.97 | 782.38 | 142.37 | 3496.72 |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
Daspalla-Buguda(22km): 140000 cum earthwork completed in Mar-24.
Buguda-Baniguchha(18Km): 295000 cum earthwork alongwith 3 minor bridges completed in Mar-24.
Baniguchha-Purunakatak(41Km): 73800cum of earthwork alongwith 2 minor bridge and 507.40m tunnel excavation in Mar-24.
Purunakatak-Boudh(22km): 21400cum of earthwork alongwith 1 major bridge completed in Mar-24.
Boudh-Sonepur(43km): Engine rolling successfully completed between Sonepur-Purunapani-Jharmunda (29.75 Km) in Mar-24. | Nuagaon-Daspalla(15.45km): CRS inspection successfully carried out on 26.07.2023.
Daspalla-Buguda(22km): 2 minor bridges completed in Jul-23.
Baniguchha-Purunakatak(38km): 2000cum of earthwork completed alongwith 1 minor bridge completed in Jul-23.
Purunakatak-Boudh(22km): 8200cum of earthwork alongwith 3 minor bridges completed in Jul-23.
Boudh-Sonepur(43km): 36100cum of earthwork alongwith 1 minor bridge in Jul-23.
Jhartarbha-Khambeswarpalli (11.20km): CRS authorisation sanctioned on 12.07.2023. |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |