Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST COAST RAILWAY.
Project Name : KHURDA ROAD-BOLANGIR(NL)ECOR.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
35503791.665089.37

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
4627.52212.7704910.22

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/202612/202612/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1437.760

Ministry Review Date

LatestLastPhysical Progress (%)Status
86Ongoing

Monthly Status

Background Information

Daspalla-Buguda (15.175 Km): 76000 cum earthwork and 9800 cum blanketing along with 33.3m tunnel lining completed in Jun-25. Buguda-Baniguchha (18.48 Km): 110000 cum earthwork and 2 minor bridges along with 251.2m tunnel lining completed in Jun-25. Launching of 11 spans (24.4m CG) girder in Br.302 alongwith 5 spans (24.4m CG) deck slab casting completed in Jun-25. Baniguchha-Purunakatak (41.435 Km): 74166 cum earthwork & 3 minor bridges along with 85m tunnel excavation and 247.4m lining completed in Jun-25. Launching of 6 spans (24.4m CG) girder in Br.435A completed. Sonepur-Purunakatak (73 Km): Hon’ble Prime Minister of India on 20.06.2025 has inaugurated the newly constructed single line of 73 Km between Sonepur-Boudh-Purunakatak of Khurda Bolangir project and also flagged off the train service between Bolangir-Sonepur-Boudh-Purunakatak.Daspalla-Buguda(22km): 140000 cum earthwork completed in Mar-24. Buguda-Baniguchha(18Km): 295000 cum earthwork alongwith 3 minor bridges completed in Mar-24. Baniguchha-Purunakatak(41Km): 73800cum of earthwork alongwith 2 minor bridge and 507.40m tunnel excavation in Mar-24. Purunakatak-Boudh(22km): 21400cum of earthwork alongwith 1 major bridge completed in Mar-24. Boudh-Sonepur(43km): Engine rolling successfully completed between Sonepur-Purunapani-Jharmunda (29.75 Km) in Mar-24.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks