Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST COAST RAILWAY.
Project Name : KHURDA ROAD-BOLANGIR(NL)ECOR.

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   29.71

Time Overrun (Months)-    213

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2923.133791.663791.66

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2571.97782.38142.373496.72

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/200912/202612/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1599.51249.5

Ministry Review Date

LatestLastPhysical Progress (%)Status
74Ongoing

Monthly Status

Background Information

Daspalla-Buguda(22km): 140000 cum earthwork completed in Mar-24. Buguda-Baniguchha(18Km): 295000 cum earthwork alongwith 3 minor bridges completed in Mar-24. Baniguchha-Purunakatak(41Km): 73800cum of earthwork alongwith 2 minor bridge and 507.40m tunnel excavation in Mar-24. Purunakatak-Boudh(22km): 21400cum of earthwork alongwith 1 major bridge completed in Mar-24. Boudh-Sonepur(43km): Engine rolling successfully completed between Sonepur-Purunapani-Jharmunda (29.75 Km) in Mar-24.Nuagaon-Daspalla(15.45km): CRS inspection successfully carried out on 26.07.2023. Daspalla-Buguda(22km): 2 minor bridges completed in Jul-23. Baniguchha-Purunakatak(38km): 2000cum of earthwork completed alongwith 1 minor bridge completed in Jul-23. Purunakatak-Boudh(22km): 8200cum of earthwork alongwith 3 minor bridges completed in Jul-23. Boudh-Sonepur(43km): 36100cum of earthwork alongwith 1 minor bridge in Jul-23. Jhartarbha-Khambeswarpalli (11.20km): CRS authorisation sanctioned on 12.07.2023.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone