Sector Name : RAILWAYS.
Agency Name : RAIL VIKAS NIGAM LTD..
Project Name : HARIDASPUR-PARADEEP(NL).

Reported Date : 07-OCT-21

Monthly Report : 9 / 2021

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1185.6402397

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2101.5725.612.192129.37

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20177/20200/0

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1000

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Project Fully Completed and commissioned on 30.07.2020. Fright trains are in operation.