Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH WESTERN RAILWAY.
Project Name : REWARI-SADULPUR-HISSAR (GC),NWR.

Reported Date : 07-MAY-10

Monthly Report : 3 / 2010

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
198.96364.19410

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
77.05300.15-306.7770.43

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
0/00/00/0

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
220

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks