Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST CENTRAL RAILWAYS.
Project Name : HAJIPUR-SUGAULI VIA VAISHALI (NL), ECR.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2066.782087.362087.36

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2273.561.46119.632454.59

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20140/012/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
215.20

Ministry Review Date

LatestLastPhysical Progress (%)Status
73Ongoing

Monthly Status

Background Information

a) Hajipur - Ghoswar (5.5 km) - Commissioned on 04.12.2016 b) Ghoswar-Vaishali (30.0 km)- Commissioned on 10.04.2020 c) Vaishali - Parukhas (15.96 km) - Commissioned on 24.01.2024 d) Parukhas- Deoria (12.89 km ) - Commissioned on 31.03.2024 e) Deoria- Sahebganj (17.6 Km) - E/work - 10.70 Lcum out of 11.0 Lcum completed, Blanketing - 0.589 Lcum out of 0.61 Lcum completed, Minor Br./RUB/LHS - 62 nos Br. completed out of total 65 nos Br., Major Bridges - Completed, Track Linking - work is in progress, OHE work is in progress, section is targeted to commission by Oct 25. d) Sahebganj - Kesaria (7.21 km):- E/work - 15.55 Lcum out of 16.5 Lcum completed, Blanketing - 0.265 Lcum out of 0.40 Lcum completed, Minor Br./RUB/LHS - 27 nos Br. completed out of total 28 nos Br., Major Bridges - 1 no out of 2 no Completed, Track Linking - work is in progress, OHE work is in progress, section is targeted to open by Nov2025 e) Kesaria - Sagauli (60.380 Km):- E/work - 42.58 Lcum out of 71.50 Lcum completed, Blanketing - 0.085 Lcum out of 2.69 Lcum completed, RUB - 12 no out of 103 no Completed, OHE work is in progress, Target - Mar26.a) Vaishali - Parukhas (16.00km) - Commissioned on 24.01.2024 b) Parukhas- Deoria (13.00km ) - E/W & Blanketing - Work in progress, Minor Br - 23 no Br completed out of total 26 Br., Major Bridges - Completed, OHE work in progress. Target month of commissioning April 24 c) Deoria- Sahebganj (17.6 Km) - E/W & Blanketing - Work in progress, Minor Br - 16 no Br completed out of total 30 Bridge (8 nos. of Minor bridge is under progress.), Major Bridge - One bridge completed out of 02 nos Br. (Bridge no.156 completed.) , OHE work in progress. Target month of commissioning - Sept 24 d) Sahebganj - Kesaria (8 km):- E/W- Work in progress, Minor Br-3 no Br completed out of total 13 Br.(6 Nos. Box completed), RUB - 6 no Br completed out of total 15 Br.(3 No. RUB under progress ( BOX completed) OHE work in progress. Target month of commissioning - Nov 24 e) Kesaria - Sagauli (60.380 Km):- E/W- Work in progress, OHE work in progress. Target month of commissioning - Mar 25

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks