Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST CENTRAL RAILWAYS.
Project Name : HAJIPUR-SUGAULI VIA VAISHALI (NL), ECR.

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   294.85

Time Overrun (Months)-    24300

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
528.652087.362087.36

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1737.92245.2143.152026.28

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
0/00/012/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
2500

Ministry Review Date

LatestLastPhysical Progress (%)Status
48Ongoing

Monthly Status

Background Information

a) Vaishali - Parukhas (16.00km) - Commissioned on 24.01.2024 b) Parukhas- Deoria (13.00km ) - E/W & Blanketing - Work in progress, Minor Br - 23 no Br completed out of total 26 Br., Major Bridges - Completed, OHE work in progress. Target month of commissioning April 24 c) Deoria- Sahebganj (17.6 Km) - E/W & Blanketing - Work in progress, Minor Br - 16 no Br completed out of total 30 Bridge (8 nos. of Minor bridge is under progress.), Major Bridge - One bridge completed out of 02 nos Br. (Bridge no.156 completed.) , OHE work in progress. Target month of commissioning - Sept 24 d) Sahebganj - Kesaria (8 km):- E/W- Work in progress, Minor Br-3 no Br completed out of total 13 Br.(6 Nos. Box completed), RUB - 6 no Br completed out of total 15 Br.(3 No. RUB under progress ( BOX completed) OHE work in progress. Target month of commissioning - Nov 24 e) Kesaria - Sagauli (60.380 Km):- E/W- Work in progress, OHE work in progress. Target month of commissioning - Mar 25"a) Vaishali ¿ Deoria (29 Km) - E/W & Blanketing - Work in progress, Minor Br-Total 23 no Br. completed out of 45 No br. (6 nos. under progress (4 Box completed)), OHE work - in progress. b) Deoria- Sahebganj (17.6 Km) - E/W-in progress, Minor Br-11 no Br completed out of total 30 Bridge (4 nos. of Minor bridge is under progress.), Major Bridge - One bridge completed out of 02 nos Br. (Bridge no.156 completed.) , OHE work in progress. Target month of commissioning - Dec¿23 c) Sahebganj - Kesaria (8 km):- E/W- in progress, Minor Br-3 no Br completed out of total 13 Br.,RUB - 6 no Br completed out of total 15 Br. OHE work in progress. Target month of commissioning - Feb¿24 d) Kesaria - Sagauli (60.380 Km):-E/W- in progress, OHE work in progress."

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone