a) Hajipur - Ghoswar (5.5 km) - Commissioned on 04.12.2016
b) Ghoswar-Vaishali (30.0 km)- Commissioned on 10.04.2020
c) Vaishali - Parukhas (15.96 km) - Commissioned on 24.01.2024
d) Parukhas- Deoria (12.89 km ) - Commissioned on 31.03.2024
e) Deoria- Sahebganj (17.6 Km) -
E/work - 10.70 Lcum out of 11.0 Lcum completed, Blanketing - 0.589 Lcum out of 0.61 Lcum completed, Minor Br./RUB/LHS - 62 nos Br. completed out of total 65 nos Br., Major Bridges - Completed, Track Linking - work is in progress, OHE work is in progress, section is targeted to commission by Oct 25.
d) Sahebganj - Kesaria (7.21 km):-
E/work - 15.55 Lcum out of 16.5 Lcum completed, Blanketing - 0.265 Lcum out of 0.40 Lcum completed, Minor Br./RUB/LHS - 27 nos Br. completed out of total 28 nos Br., Major Bridges - 1 no out of 2 no Completed, Track Linking - work is in progress, OHE work is in progress, section is targeted to open by Nov2025
e) Kesaria - Sagauli (60.380 Km):-
E/work - 42.58 Lcum out of 71.50 Lcum completed, Blanketing - 0.085 Lcum out of 2.69 Lcum completed, RUB - 12 no out of 103 no Completed, OHE work is in progress, Target - Mar26. | a) Vaishali - Parukhas (16.00km) - Commissioned on 24.01.2024
b) Parukhas- Deoria (13.00km ) - E/W & Blanketing - Work in progress, Minor Br - 23 no Br completed out of total 26 Br., Major Bridges - Completed, OHE work in progress. Target month of commissioning April 24
c) Deoria- Sahebganj (17.6 Km) -
E/W & Blanketing - Work in progress, Minor Br - 16 no Br completed out of total 30 Bridge (8 nos. of Minor bridge is under progress.), Major Bridge - One bridge completed out of 02 nos Br. (Bridge no.156 completed.) , OHE work in progress. Target month of commissioning - Sept 24
d) Sahebganj - Kesaria (8 km):-
E/W- Work in progress, Minor Br-3 no Br completed out of total 13 Br.(6 Nos. Box completed), RUB - 6 no Br completed out of total 15 Br.(3 No. RUB under progress ( BOX completed) OHE work in progress. Target month of commissioning - Nov 24
e) Kesaria - Sagauli (60.380 Km):- E/W- Work in progress, OHE work in progress. Target month of commissioning - Mar 25 |