Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST CENTRAL RAILWAYS.
Project Name : HAJIPUR-SUGAULI VIA VAISHALI (NL), ECR.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   294.85

Time Overrun (Months)-    24324

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
528.652087.362087.36

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1776.7395.39101.412273.5

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
0/00/012/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
288420.41

Ministry Review Date

LatestLastPhysical Progress (%)Status
73Ongoing

Monthly Status

Background Information

a) Vaishali - Parukhas (15.96 km) - Commissioned on 24.01.2024 b) Parukhas- Deoria (13.00 km ) - Commissioned on 31.03.2024 c) Deoria- Sahebganj (17.6 Km) - E/W & Blanketing - Work in progress, Minor Br - completed, Major Bridge - completed, Track Linking - Work in progress, OHE work in progress. Target month of commissioning - July 25 d) Sahebganj - Kesaria (7.21 km):- E/W & Blanketing - Work in progress, Minor Br.- 14 no Br completed out of total 16 Br., RUB - 13 no Br completed out of total 14 Br.Track Linking - Work in progress. OHE work in progress. Target month of commissioning - Dec 25 e) Kesaria - Sagauli (60.380 Km):- E/W- Work in progress, Minor Br.- 9 nos Br. completed out of total 99 nos Br.,RUB - 12 nos Br. completed out of total 103 nos Br., OHE work in progress. Target month of commissioning - Dec 26 a) Vaishali - Parukhas (16.00km) - Commissioned on 24.01.2024 b) Parukhas- Deoria (13.00km ) - E/W & Blanketing - Work in progress, Minor Br - 23 no Br completed out of total 26 Br., Major Bridges - Completed, OHE work in progress. Target month of commissioning April 24 c) Deoria- Sahebganj (17.6 Km) - E/W & Blanketing - Work in progress, Minor Br - 16 no Br completed out of total 30 Bridge (8 nos. of Minor bridge is under progress.), Major Bridge - One bridge completed out of 02 nos Br. (Bridge no.156 completed.) , OHE work in progress. Target month of commissioning - Sept 24 d) Sahebganj - Kesaria (8 km):- E/W- Work in progress, Minor Br-3 no Br completed out of total 13 Br.(6 Nos. Box completed), RUB - 6 no Br completed out of total 15 Br.(3 No. RUB under progress ( BOX completed) OHE work in progress. Target month of commissioning - Nov 24 e) Kesaria - Sagauli (60.380 Km):- E/W- Work in progress, OHE work in progress. Target month of commissioning - Mar 25

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone