Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST CENTRAL RAILWAYS.
Project Name : KOSI BRIDGE (NL), ECR.

Reported Date : 08-MAR-22

Monthly Report : 2 / 2022

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
499.41516.02516.02

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
447.35146.7468.05

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20200/012/2021

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
34.950

Ministry Review Date

LatestLastPhysical Progress (%)Status
93Completed

Monthly Status

Background Information

commissioned

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks