Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST CENTRAL RAILWAYS.
Project Name : KODERMA-TILAIYA (NL), ECR.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1625.871625.871700

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1958.2755.3225.932039.52

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20230/012/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
3000

Ministry Review Date

LatestLastPhysical Progress (%)Status
80Ongoing

Monthly Status

Background Information

a) Tilaiya - Laundh - Kheraundh (24 km) - Commissioned on 16.02.2018. b) Koderma – Jharahi (17.50 km) - Section commissioned on 27.03.2023 c) Jharahi – Jamundaha (9.556 km) - Section commissioned on 30.03.2024 for Good Traffic. d) Jamundaha - Kheraundh (14.96 km) - E/work - 90.335 Lcum out of 95.57 Lcum completed. & Blanketing - 8700 cum out of 21000 cum completed, Minor Br./LHS/RUB - 28 nos Br. completed out of total 32 nos Br., Major Bridges - 4 nos Br.completed out of total 7 nos Br., & OHE work is in progress. Critical Issue:- Construction of 4 Nos. of Tunnels (1175 m) & Balance earthwork of 5.5 lakh cum. Target month of commissioning Mar’26.a) Tilaiya - Laundh - Kheraundh (24 km) - Commissioned on 16.02.2018. b) Koderma – Jharahi (17.50 km) - Section commissioned on 27.03.2023 c) Jharahi – Jamundaha (9.5 km) - Commissioned for Goods train on 30.03.24 d) Jamundaha - Kheraundh (15 km) - Work in progress. Target month of commissioning Mar’25.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Forest Land10/20050/0PendingNormal