a) Tilaiya - Laundh - Kheraundh (24 km) - Commissioned on 16.02.2018.
b) Koderma – Jharahi (17.50 km) - Section commissioned on 27.03.2023
c) Jharahi – Jamundaha (9.556 km) - Section commissioned on 30.03.2024 for Good Traffic.
d) Jamundaha - Kheraundh (15.08 km) - E/W in cutting - 94% Completed, E/W in Filling - 82% Completed, & Blanketing - 41% Completed, Minor bridges - 24 nos Br. completed out of total 29 nos Br., Major Bridges - 4 nos Br.completed out of total 7 nos Br., RUB/LHS - completed & OHE work is in progress.
Critical Issue:- Construction of 4 Nos. of Tunnels (1175 m) and Bridge No. 106 (24 x 30.5 m CG).
Target month of commissioning Mar’26. | a) Tilaiya - Laundh - Kheraundh (24 km) - Commissioned on 16.02.2018.
b) Koderma – Jharahi (17.50 km) - Section commissioned on 27.03.2023
c) Jharahi – Jamundaha (9.5 km) -
Commissioned for Goods train on 30.03.24
d) Jamundaha - Kheraundh (15 km) - Work in progress.
Target month of commissioning Mar’25. |