Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST CENTRAL RAILWAYS.
Project Name : KODERMA-TILAIYA (NL), ECR.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   269.64

Time Overrun (Months)-    24312

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
459.911625.871700

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1621.39269.6167.271958.27

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
0/00/012/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
2750

Ministry Review Date

LatestLastPhysical Progress (%)Status
80Ongoing

Monthly Status

Background Information

a) Tilaiya - Laundh - Kheraundh (24 km) - Commissioned on 16.02.2018. b) Koderma – Jharahi (17.50 km) - Section commissioned on 27.03.2023 c) Jharahi – Jamundaha (9.556 km) - Section commissioned on 30.03.2024 for Good Traffic. d) Jamundaha - Kheraundh (15.08 km) - E/W in cutting - 94% Completed, E/W in Filling - 82% Completed, & Blanketing - 41% Completed, Minor bridges - 24 nos Br. completed out of total 29 nos Br., Major Bridges - 4 nos Br.completed out of total 7 nos Br., RUB/LHS - completed & OHE work is in progress. Critical Issue:- Construction of 4 Nos. of Tunnels (1175 m) and Bridge No. 106 (24 x 30.5 m CG). Target month of commissioning Mar’26.a) Tilaiya - Laundh - Kheraundh (24 km) - Commissioned on 16.02.2018. b) Koderma – Jharahi (17.50 km) - Section commissioned on 27.03.2023 c) Jharahi – Jamundaha (9.5 km) - Commissioned for Goods train on 30.03.24 d) Jamundaha - Kheraundh (15 km) - Work in progress. Target month of commissioning Mar’25.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Forest Land10/20050/0PendingNormal

Ongoing Milestone

Completed Milestone