a) Tilaiya - Laundh - Kheraundh (24 km) - Commissioned on 16.02.2018.
b) Koderma – Jharahi (17.50 km) - Section commissioned on 27.03.2023
c) Jharahi – Jamundaha (9.556 km) - Section commissioned on 30.03.2024 for Good Traffic.
d) Jamundaha - Kheraundh (14.96 km) - E/work - 90.335 Lcum out of 95.57 Lcum completed. & Blanketing - 8700 cum out of 21000 cum completed, Minor Br./LHS/RUB - 28 nos Br. completed out of total 32 nos Br., Major Bridges - 4 nos Br.completed out of total 7 nos Br., & OHE work is in progress.
Critical Issue:- Construction of 4 Nos. of Tunnels (1175 m) & Balance earthwork of 5.5 lakh cum.
Target month of commissioning Mar’26. | a) Tilaiya - Laundh - Kheraundh (24 km) - Commissioned on 16.02.2018.
b) Koderma – Jharahi (17.50 km) - Section commissioned on 27.03.2023
c) Jharahi – Jamundaha (9.5 km) -
Commissioned for Goods train on 30.03.24
d) Jamundaha - Kheraundh (15 km) - Work in progress.
Target month of commissioning Mar’25. |