a) Tilaiya - Laundh - Kheraundh (24 km) - Commissioned on 16.02.2018.
b) Koderma – Jharahi (17.50 km) - Section commissioned on 27.03.2023
c) Jharahi – Jamundaha (9.5 km) -
Commissioned for Goods train on 30.03.24
d) Jamundaha - Kheraundh (15 km) - Work in progress.
Target month of commissioning Mar’25. | "Koderma ¿ Jharahi (17.50 km) - Section commissioned on 27.03.2023
Kheraundh ¿ Tilaiya (24 km) - Commissioned.
Jharahi ¿ Jamundaha (10 km) -
E/W - Work in progress & Minor Br. 12 no Br. completed out of total 18 no Br. , Major Br. - Work in progress, RUB/LHS - Completed, OHE work in progress. Target month of commissioning Dec¿23." |