Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST CENTRAL RAILWAYS.
Project Name : PATNA GANGA BRIDGE (NL), ECR.

Reported Date : 09-SEP-16

Monthly Report : 7 / 2016

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
624.472921.463142.46

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
3079.6725.2503104.92

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/20072/20162/2016

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
221221

Ministry Review Date

LatestLastPhysical Progress (%)Status
30-JUN-160Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Forest Land10/20050/0PendingNormal