Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : WEST CENTRAL RAILWAY.
Project Name : RAMGANJMUNDI-BHOPAL (NL),WCR.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   1107.06

Time Overrun (Months)-    63

Total/Pending/Completed Milestone - 15 / 6 / 9

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
424.63032.465125.16

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2485.38803.3398.943387.65

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/202112/20256/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
6500

Ministry Review Date

LatestLastPhysical Progress (%)Status
27-JUL-2069Ongoing

Monthly Status

Background Information

Ballast supply- 8000 cum Earthwork: 1.24 lakh Cubic meters BALLAST: 10000 Cum ROB No. 1 completed. NAYAGAON-KHILCHIPUR SECTION AND SHRN-JHARKHEDA SECTION COMMISSIONED.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Forest Land11/20050/0PendingNormal
Others11/20050/0PendingNormal

Ongoing Milestone

Completed Milestone