Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : WEST CENTRAL RAILWAY.
Project Name : RAMGANJMUNDI-BHOPAL (NL),WCR.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 15 / 6 / 9

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
30323032.465125.16

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
3387.6536.2589.193513.09

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/202512/20256/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
834.35125.16

Ministry Review Date

LatestLastPhysical Progress (%)Status
27-JUL-2069Ongoing

Monthly Status

Background Information

Khilchipur - Biaora section Earthwork in filling -1,28,850 Cum Earthwork in Cutting - 47200 Cum Ballast supply - 1000 Cum Track linking - 2.4 TKM Rajgarh Station Building, Rajgarh & Narsingpura Platform - work in progress. ROB No. 14: Sub structure completed. 18 M Girder arrived at site and assembling under progress. Br. No. 208- 2nd lift of wall done Br. No. 209- 1st Segment of Bottom Slab done Br. No. 210- Bottom Slab done Br. No. 211 – Return R1& R3 1st lift done Br. No. 212- Earthwork in filling in progress Br. No. 249-A- Excavation in progress Br. No. 218 - Right side approach 30 M completed, 20 M Bottom Raft casted, Left side U-Return wall excavation in progress Br. No. 225- Left side approach 70 M completed and 49 M Bottom Raft casted Br. No. 230A- Box PCC, Bottom Slab, Bottom Haunch & both wall 1st lift casted. Br. No. 237- Wing Return W2R2 & W4R4 excavation in progress Br. No. 238 - Abutment A1, A2, U wall and Return wall U1, R1 & U2, R2, U3, R3 & U4 R4 in progress. Br. No. 246 - Abutment A1, A2 completed, U wall and Return wall U1R1, U1R2, U2R3 & U4R4 Work in progress. Br. No. 247 - Completed Br. No. 247A - Box completed Br. No. 248 - PCC done Br. No. 249 - 1st segment 2nd lift casted, 2nd segment bottom haunch casted Br.No.250 - 1st Segment bottom haunch casted,2nd segment bottom raft casted. Br.No.251 - Foundation excavation in progress Rajgarh - Biaora Section Earthwork in filling - 16400 Cum Earthwork in Cutting - 12700 Cum Ballast supply - 1500 Cum Sleepers transportation - 8000 Nos. Br. No. 252(Newaj Br)- Open foundation - all 22 completed, Pier/Abutment Shaft- 01 completed. Bed Block - 04 completed, Pedestal - 04 completed Girder launching - 03 done, U-Wall behind Abutment - A1 F3 Raft casted & A2 F3 reinforcement in progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Forest Land11/20050/0PendingNormal
Others11/20050/0PendingNormal