Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : WEST CENTRAL RAILWAY.
Project Name : RAMGANJMUNDI-BHOPAL (NL),WCR.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   69.04

Time Overrun (Months)-    6

Total/Pending/Completed Milestone - 15 / 6 / 9

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
30323032.465125.16

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
3387.6536.2503423.9

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/202512/20256/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
834.35125.16

Ministry Review Date

LatestLastPhysical Progress (%)Status
27-JUL-2069Ongoing

Monthly Status

Background Information

Ballast supply- 6500 cum Earth work in filling- 129000 cum Earthwork in Cutting - 82000 cum Rails transportation- 3.2 TKM Br No. 208- Bottom Slab & 1st lift of wall casted. Br No. 212- Substructure complete. Pedestal casted Br No. 214- Completed Br No. 218- Right side approach road excavation in progress. Box completed. Br No. 225- Left side approach completed and Bottom Raft and 2nd lift casted Br No. 228 - Completed Br No. 230A- Box excavation work completed Br No. 237- Wing Return W3R3 , W1R1 & W2R2 completed & W4R4 excavation work in progress Br No.238- Abutment A1& A2 casted, U & Return wall U1R1, U2R2, U2R3 casted Br No.246- Abutment A1& A2 completed, U & Return wall U1R1, U1R, U2R3 & U2R4 casted Br No.239A- Box completed, Left side approach road & Bottom Raft casted Br No.245- Return wall 1st lift both side casted Br No.247- Wing Return W2R2 completed, W4R4 - Bottom Raft casted Br No.247A- Bottom Slab casted Br No.249- 1st segment bottom raft casted, 2nd segment bottom raft in progress Rajgarh - Biaora Section Earth work in filling - 1600 cum Earth work in Cutting - 23400 cum Sleeper Transportation- 500 Nos Newaj Br No.252- Pile Cap-01 casted, Pier /Abutment shaft 03 casted, Bed Block 02 done, Pedestal 01 casted, Girder launching 07 done overall 11 Girders launched, Abutment A1 & A2 reinforcement work in progress Br No.266A- Completed Br No.274- Wing Return W1R1 3rd lift, W2R2 1st lift, W3R3 3rd lift casted, W4R4 - 2nd lift casted Br No.277- Sub structure completed Br No.279- Box completed, Wing Return W1R1 PCC done, W3R3 - excavation is done Br No.280- Box completed Br No.281- Abutment A1 casted, Abutment A2 - Bottom raft casted, Pier P1 & P2- bottom raft reinforcement work in progress Br No.283- Wing Return W1R1 & W3R3 excavation in progress Br No.284- Abutment A1 & A2 PCC done Br No.285- Completed

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Forest Land11/20050/0PendingNormal
Others11/20050/0PendingNormal

Ongoing Milestone

Completed Milestone