Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : WEST CENTRAL RAILWAY.
Project Name : RAMGANJMUNDI-BHOPAL (NL),WCR.

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   614.19

Time Overrun (Months)-    57

Total/Pending/Completed Milestone - 15 / 8 / 7

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
424.62909.993032.46

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1889.8595.5802485.38

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/202112/202512/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
800800

Ministry Review Date

LatestLastPhysical Progress (%)Status
27-JUL-2067Ongoing

Monthly Status

Background Information

"Aklera to Ghatoli Section- Tunnel T-3 completed. Face wall R1&R2 completed, Drain 400 m completed ? Earth work in Cutting 27000 m3 ? Earth work in Filling 56000 m3 ? Ballast supply 7300 m3 ? Track Linking 5.70 TKM ? ROB 3: RE PANEL 100 square meters , Crash barrier 115 Nos. casted. Girder launching and deck slab casting completed. 260 Nos. RE PANEL erected. ? Br No. 135 completed Ghatoli station building completed and handed over to S&T department. Platform wall 100 M masonry work completed. ? Bridge No. 133B -RCC 100 m3, PCC -34 m3 ? Br. No.133 and 133A approaches completed ? Br.No.127 PSC. Girder & Deck Slab casted Ghatoli-Nayagaon Section- Earth work in Cutting- 32400 m3 ? Earth work in Filling - - 24700 m3 ? Tunnel T4: 108 M Excavation , Shotcrete , Rockbolting, Back fill total 1166M out of 1230 M completed ? Br No. 136 Height Gauge foundation work completed. ? Br No.165- Excavation of Wing/Return wall and PCC done. ? Br No.166- casting of bottom slab and 1st lift done ? Br No 138 Wing and Return W2R2 and W4R4 completed. ? Br. No. 142 B , Return wall R3 & R4 completed and Composite girder reached at site ( span 18.3m.) Nayagaon - Khilchipur section- ? Earth work in cutting-46000 m3 ? Earth work in filling-51800 m3 Khilchipur ? Rajgarh-Biaora Section- "

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Forest Land11/20050/0PendingNormal
Others11/20050/0PendingNormal

Ongoing Milestone

Completed Milestone