Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTH EAST CENTRAL RAILWAY.
Project Name : CHHINDWARA - NAGPUR (GC)(SECR).

Reported Date : 07-OCT-21

Monthly Report : 9 / 2021

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
383.791413.761511.5

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1420.648.5419.381448.56

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
0/08/20208/2020

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
4646

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Project complete and commissioned on 28.8.20

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks