Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : JAIPUR BYPASS PH:II (GQ) KM 221 OF NH-8 - KM 246 OF NH-11.

Reported Date : 18-JUL-06

MOU Status :

Monthly Report : 3 / 2005

Cost Overrun (%)-   0

Time Overrun (Months)-    9

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2100210

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
16723.60190.6

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20040/03/2005

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
41.450

Ministry Review Date

LatestLastPhysical Progress (%)Status
28-JAN-050Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone