Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : TADA-CHENNAI (GQ) KM.52.8-KM.11 (NH-5).

Reported Date : 18-JUL-06

Monthly Report : 12 / 2005

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2330233

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
273.17.50280.6

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20030/012/2005

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
10.750

Ministry Review Date

LatestLastPhysical Progress (%)Status
28-JAN-050Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks