Project Summary
Project Summary
Sector Name : ROAD TRANSPORT AND HIGHWAYS.
Agency Name : NATIONAL HIGHWAYS AUTHORITY OF INDIA.
Project Name : ORAI TO JHANSI (UP-5),NH-25, KM.220.0 TO KM.170.0.

Reported Date : 25-JUL-13

MOU Status :

Monthly Report : 5 / 2013

Cost Overrun (%)-   0

Time Overrun (Months)-    62

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
340.680340.68

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
36700400.56

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20080/05/2013

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone