Sector Name : TELECOMMUNICATIONS.
Agency Name : MAHANAGAR TELEPHONE NIGAM LIMITED.
Project Name : DELHI CDMA IN WLL (MTNL).

Reported Date : 18-JUL-06

Monthly Report : 1 / 2006

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
460.280460.28

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
34.356.65041

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/20040/01/2006

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
30.972.9

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks