Project Summary
Project Summary
Sector Name : TELECOMMUNICATIONS.
Agency Name : BHARAT SANCHAR NIGAM LIMITED.
Project Name : CHENNAI PHASE-III CMTS (BSNL).

Reported Date : 18-JUL-08

Monthly Report : 11 / 2007

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
233.210233.21

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
00072.3

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20040/00/0

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks