Project Summary
Project Summary
Sector Name : TELECOMMUNICATIONS.
Agency Name : MAHANAGAR TELEPHONE NIGAM LIMITED.
Project Name : EXPANSION OF GSM 400 (MTNL) (MUMBAI).

Reported Date : 16-FEB-09

Monthly Report : 12 / 2008

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
216.370216.37

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
0110.960110.96

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
1/20050/012/2008

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks