Project Summary
Project Summary
Sector Name : URBAN DEVELOPMENT.
Agency Name : MAHARASTRA METRO RAIL CORPORATION LTD..
Project Name : DELHI MRTS PHASE-II PROJECT.

Reported Date : 03-NOV-11

Monthly Report : 8 / 2011

  

   

Total/Pending/Completed Milestone - 10 / 0 / 10

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
8676018894.36

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
17467.38836.92018304.3

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20100/06/2011

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
2017.333791.47

Ministry Review Date

LatestLastPhysical Progress (%)Status
30-JUN-10100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Land Acquisition10/20060/0PendingNormal