Reported Date :
10-SEP-24
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
8
/
2024
|
Cost Overrun (%)- 96.5
|
Time Overrun (Months)-
99
|
Total/Pending/Completed Milestone -
70
/
0
/
70
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
| Present Status/Major activities completed during March 2024:
KAPP-3:
The first largest indigenous 700 MWe Unit started operation at full capacity from August 30, 2023.
KAPP-4:
The Unit has been declared commercial from March 31, 2024. Currently the Unit is operating at 50% full power.
The Commissioning and Operationalisation of KAPP-4 is achieved in March 2024 and with this Kakrapar Atomic Power Project Units-3&4 is completed.
|
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |