Project Summary
Project Summary
Sector Name : ATOMIC ENERGY.
Agency Name : NUCLEAR POWER CORPORATION OF INDIA LIMITED.
Project Name : KAKRAPAR ATOMIC POWER PROJECT - 3 AND 4.

Reported Date : 09-JUL-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 6 / 2024

Cost Overrun (%)-   96.5

Time Overrun (Months)-    99

Total/Pending/Completed Milestone - 70 / 0 / 70

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
114592251722517

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
21222257021479

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20150/03/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
3020

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Ongoing

Monthly Status

Background Information

Present Status/Major activities completed during March 2024: KAPP-3: The first largest indigenous 700 MWe Unit started operation at full capacity from August 30, 2023. KAPP-4: The Unit has been declared commercial from March 31, 2024. Currently the Unit is operating at 50% full power. The Commissioning and Operationalisation of KAPP-4 is achieved in March 2024 and with this Kakrapar Atomic Power Project Units-3&4 is completed.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone