Project Summary
Project Summary
Sector Name : CIVIL AVIATION.
Agency Name : AIRPORT AUTHORITY OF INDIA LIMITED.
Project Name : EXTENSION OF SECONDARY RUNWAY, CONSTRUCTION OF TAXI TRACKS AT CHENNAI AIRPORT(K2).

Reported Date : 04-JUL-11

Monthly Report : 4 / 2011

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2300230

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
188.12053.16253.6

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
1/20110/00/0

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks